New construction of the Paul-Gerhardt-Allee primary school with gymnasium in Munich

Paul Gerhardt Allee in 81925 München

No items found.
Construction execution:
2020
-
2021
Size in sqm:
3800

Technology

3800 sqm of 8mm fiber cement facade visibly mounted on stainless steel/aluminum substructure. 250 sqm of aluminum sheet cassette facade invisibly attached to stainless steel/aluminum substructure. Boulder wall installation. ABS safety system installation. Fiber cement panel installation including acoustic panels on aluminum substructure. Thermal insulation, connection plates, base plates, lintel cladding, reveal cladding, exterior and interior corners, penetrations, etc. Perforated fiber cement panels and fiber cement panels as wallpaper door cladding.

Client/Contractor

Prudens GmbH

Additional images of the project